How many working days in year 2012?
Here is the detail of the calculation:
Because 2012 is a leap year, it has 366 days.
Let's remove 52 saturdays and 53 sundays. It remains 261 days.
Now, let's remove 9 public holidays that do not fall during a weekend and we obtain 252 working days in 2012.
Here is the list of these 9 public holidays:
1. New Year's Day (substitute day) : понедельник, 2 январь, 2012
2. Good Friday : пятница, 6 апрель, 2012
3. Easter Monday : понедельник, 9 апрель, 2012
4. Early May Bank Holiday : понедельник, 7 май, 2012
5. Spring Bank Holiday : понедельник, 4 июнь, 2012
6. Queen's Diamond Jubilee : вторник, 5 июнь, 2012
7. Late Summer Bank Holiday : понедельник, 27 август, 2012
8. Christmas Day : вторник, 25 декабрь, 2012
9. Boxing Day : среда, 26 декабрь, 2012